For an integrated
utility in the power generation business, the issue
of market power is critical. When utilities were regulated
solely under cost-based (cost-of-service) rates, such
concerns were moot, but this issue has become paramount
as competitive wholesale markets have grown.
In recent years, the U.S. Federal Energy Regulatory
Commission (FERC) has struggled to find the best ways
to determine whether a wholesale supply applicant (e.g.,
a utility or an independent power provider (IPP)) could
benefit from its generation portfolio by influencing
the wholesale price of power in the market—thus
affecting customers—and if so, what to do about
it. This determination is vital, since a FERC finding
of market power would indicate that a utility would need
to correct that situation by selling capacity; changing
its wholesale, market-based rates (MBR) to cost-based
rates; or undertaking other mitigation approaches. |
This article was published
in the Spring/Summer 2005 issue
of Perspectives.
Please refer to our Terms
of Use policy regarding acceptable
use of content on the ICF International Web
site. |
|
Is it easy to determine whether wholesale market power exists?
No. FERC has made several attempts to identify and mitigate
the potential for generation market power since MBR was first
introduced in 1989. For example, in November 2001, FERC replaced
its “hub-and-spoke” method
with the Supply Margin Analysis (SMA) after realizing the
former method’s limitations. The SMA used a market
share benchmark (which the previous test had not) of 20 percent
or more in each relevant market. Also, the SMA took transmission
constraints into account, allowing FERC to more precisely
estimate the amount of generation that could compete with
the utility and establishing a threshold to determine whether
its supply was pivotal in the market.

However, the SMA had its shortcomings. It did not consider
that generation dedicated to native load (end-use utility
customers) and other wholesale commitments could not influence
market prices, and it did not allow utilities to challenge
FERC if they failed the market power test. Thus, in April
2004, FERC replaced the SMA with two interim, indicative
screens. The screens are “interim” because FERC
established a proceeding to conduct a comprehensive review
of its test. Unlike the SMA, they are "indicative" because
they give applicants a chance to rebut a market power finding.
For example, in the Uncommitted Pivotal Supplier (UPS) analysis,
FERC considers native load and other firm contracts in calculating
its uncommitted capacity at peak times. FERC replaced the
SMA’s use of total transfer capability (TTC) with simultaneous
import capability to better measure the effect of transmission
limitations on generation imports. In the Uncommitted Market
Share (UMS) analysis, FERC evaluates the applicant’s
share of the seasonal uncommitted capacity. FERC believes
that, taken together, these screens give a reasonable indication
of whether an applicant may possess market power. Failure
in either screen creates a “rebuttable presumption” of
market power in generation. Several utilities (e.g., Entergy,
Southern, and AEP) failed one or both of these tests. In
its recent application to acquire PSEG, Exelon has acknowledged
that it will fail these tests and has offered to sell power
plants or sign contracts to sell the output of 5,500 megawatts
of generation. This approach could be an important indicator
of how FERC intends to apply its market power screens.
If the utility challenges the test findings
of potential market power, it can submit more detailed data
using a "delivered
price test" (DPT) to illustrate that it has not exercised
such influence in actual practice. The DPT incorporates capacity
that can be delivered at a price less than or equal to 105
percent of the market price into the destination market,
and is applied in two prongs—one looking at "economic
capacity" (EC) and the other at "available economic
capacity" (AEC). EC includes all capacity for suppliers
who can compete in the market using the 105 percent threshold
if simultaneous import capability is available, while AEC
excludes the supplier’s native load and other firm
commitments. If FERC remains unconvinced by the rebuttal,
the commission may require utilities to adopt the mitigation
procedures mentioned above. Figure 1 describes the overall
process.
To date, more than 100 entities have made filings
under the interim tests, a number of which have been accepted;
some filings have triggered rate reviews (206 filings). To
maintain MBR, utilities like Entergy will continue to walk
the tightrope of allaying FERC’s concerns while satisfying
native load obligations. The interim screens and the DPT
are not perfect either—FERC may need to define the
appropriate product and geographic markets (e.g., products
may include capacity, spinning reserves, regulations, etc.).
Moreover, focusing on only annual, seasonal, or aggregate
load can be misleading, since each hour represents a product
market with a unique supply curve. Similarly, using the utility
control area— or regional transmission organizations
(RTO)—as the
default geographic market may be inappropriate, and “commercially
significant transmission constraints” could more accurately
outline the relevant market. Many of these shortcomings could
be addressed through the use of detailed market analysis,
using state-of-the-art generation and transmission models.
Finally, FERC’s market power assessments include more
than just generation—they also intend to include transmission
tests, assessments of affiliate abuse, and barriers to entry.
Recognizing these issues, FERC has recently opened a new
docket (RM04-7-000) to consider how to mesh all four prongs
of its market power evaluation. The results of this review
will inevitably affect power companies for years to come.
Learn more about ICF International’s power market
services.

|